Project 2019 For Dummies®
Published by: John Wiley & Sons, Inc., 111 River Street, Hoboken, NJ 07030-5774, www.wiley.com
Copyright © 2019 by John Wiley & Sons, Inc., Hoboken, New Jersey
Published simultaneously in Canada
No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means, electronic, mechanical, photocopying, recording, scanning or otherwise, except as permitted under Sections 107 or 108 of the 1976 United States Copyright Act, without the prior written permission of the Publisher. Requests to the Publisher for permission should be addressed to the Permissions Department, John Wiley & Sons, Inc., 111 River Street, Hoboken, NJ 07030, (201) 748-6011, fax (201) 748-6008, or online at http://www.wiley.com/go/permissions.
Trademarks: Wiley, For Dummies, the Dummies Man logo, Dummies.com, Making Everything Easier, and related trade dress are trademarks or registered trademarks of John Wiley & Sons, Inc. and may not be used without written permission. Microsoft is a registered trademark of Microsoft Corporation. All other trademarks are the property of their respective owners. John Wiley & Sons, Inc. is not associated with any product or vendor mentioned in this book.
LIMIT OF LIABILITY/DISCLAIMER OF WARRANTY: THE PUBLISHER AND THE AUTHOR MAKE NO REPRESENTATIONS OR WARRANTIES WITH RESPECT TO THE ACCURACY OR COMPLETENESS OF THE CONTENTS OF THIS WORK AND SPECIFICALLY DISCLAIM ALL WARRANTIES, INCLUDING WITHOUT LIMITATION WARRANTIES OF FITNESS FOR A PARTICULAR PURPOSE. NO WARRANTY MAY BE CREATED OR EXTENDED BY SALES OR PROMOTIONAL MATERIALS. THE ADVICE AND STRATEGIES CONTAINED HEREIN MAY NOT BE SUITABLE FOR EVERY SITUATION. THIS WORK IS SOLD WITH THE UNDERSTANDING THAT THE PUBLISHER IS NOT ENGAGED IN RENDERING LEGAL, ACCOUNTING, OR OTHER PROFESSIONAL SERVICES. IF PROFESSIONAL ASSISTANCE IS REQUIRED, THE SERVICES OF A COMPETENT PROFESSIONAL PERSON SHOULD BE SOUGHT. NEITHER THE PUBLISHER NOR THE AUTHOR SHALL BE LIABLE FOR DAMAGES ARISING HEREFROM. THE FACT THAT AN ORGANIZATION OR WEBSITE IS REFERRED TO IN THIS WORK AS A CITATION AND/OR A POTENTIAL SOURCE OF FURTHER INFORMATION DOES NOT MEAN THAT THE AUTHOR OR THE PUBLISHER ENDORSES THE INFORMATION THE ORGANIZATION OR WEBSITE MAY PROVIDE OR RECOMMENDATIONS IT MAY MAKE. FURTHER, READERS SHOULD BE AWARE THAT INTERNET WEBSITES LISTED IN THIS WORK MAY HAVE CHANGED OR DISAPPEARED BETWEEN WHEN THIS WORK WAS WRITTEN AND WHEN IT IS READ.
For general information on our other products and services, please contact our Customer Care Department within the U.S. at 877-762-2974, outside the U.S. at 317-572-3993, or fax 317-572-4002. For technical support, please visit https://hub.wiley.com/community/support/dummies.
Wiley publishes in a variety of print and electronic formats and by print-on-demand. Some material included with standard print versions of this book may not be included in e-books or in print-on-demand. If this book refers to media such as a CD or DVD that is not included in the version you purchased, you may download this material at http://booksupport.wiley.com. For more information about Wiley products, visit www.wiley.com.
Library of Congress Control Number: 2018967613
ISBN 978-1-119-56512-3 (pbk); ISBN 978-1-119-56509-3 (ebk); ISBN 978-1-119-56514-7 (ebk)
Over the years, project management has evolved from a discipline that began with index cards and yarn to one that now uses sophisticated analyses, techniques, projections, reporting, and time and money tracking. Project management software brings functionality to project management that makes planning and tracking the complex projects we undertake a little more manageable.
Microsoft Office Project 2019, the most recent incarnation of the world’s most popular project management software, offers a tremendous wealth of functionality to users. In the beginning, however, as with most software, mastering it can seem like a daunting process. It helps to understand how Project’s features relate to what you do every day as a project manager.
In Project 2019 For Dummies, my goal is to help you explore Project 2019, providing information on relevant project management concepts while also offering specific procedures to build and track a Project schedule.
Here are some broad topics that I help you explore in this book. You can:
Throughout this book, I offer advice on how to make all these features and procedures mesh with what you already know as a project manager to ease the transition to using Project 2019.Within this book, you may note that some web addresses break across two lines of text. If you’re reading this book in print and want to visit one of these web pages, simply key in the web address exactly as it’s noted in the text, pretending as though the line break doesn’t exist. If you’re reading this as an e-book, you’ve got it easy — just click the web address to be taken directly to the web page.
Finally, Microsoft Office only runs on Windows 10 (as of this printing), and not Windows 7 or 8.1, so you’ll need to have Windows 10 in order to run Project 2019. This book is written as if you’re using the “stand-alone” or “one-time-purchase” version of Microsoft Project. If you have an Office 365 subscription, you may already be familiar with Project 2019 features, because they’re added to previous versions of Project biannually. Because this book assumes stand-alone software, I don’t spend time on project management service features; the Roadmap service; or anything associated with enterprise versions, server features, or cloud functionality. But the good news is, regardless of whether you’re running the stand-alone or subscription version of the software, this book is packed full of useful information for getting to know Project 2019.
I’ve made some assumptions about you, gentle reader. I figure that you’re computer-literate and that you know how to use the mouse, the keyboard, and the Ribbon. I assume that you know how to use most common Windows functions (such as the Clipboard), as well as many basic software functions, such as selecting text and dragging and dropping items with the mouse.
I also assume that you have experience in managing projects. Whether you manage very large projects that are several years long or you have been a team lead on a project, the information in this book is more accessible if you have a background in project management.
I do not assume that you’ve used Project or any other project management software. If you’re new to Project, you’ll find what you need to get up to speed, including information on how Project works, finding your way around the Project interface, and building your first Project plan. If you’ve used an earlier version of Project, you’ll find out about Project 2019 and the features it provides.
One picture is worth … well, you know. That’s why For Dummies books use icons to provide visual clues to what’s going on. Essentially, icons call your attention to bits of special information that may well make your life easier. The following icons are used in this book.
In addition to what you’re reading right now, this product also comes with a free access-anywhere Cheat Sheet that includes tips on creating your project schedule, shortcut keys, and helpful websites to hone your expertise. To get this Cheat Sheet, simply go to www.dummies.com and type Project 2019 For Dummies Cheat Sheet in the Search box.
Take what you’ve learned in the project management school of hard knocks and jump into the world of Project 2019. When you do, you’ll be rewarded with a wealth of tools and information that help you manage your projects much more efficiently.
Your first step might be to read the table of contents and find the sections of this book that you need — or simply turn to Chapter 1 and start reading.
Part 1
IN THIS PART …
Get familiar with the Ribbons and its tabs in Project 2019.
See how to open a new project, enter tasks, and organize a project.
Become skilled in working with summary tasks, milestones, and notes.
Identify and arrange task dependencies to create a network diagram.
Develop duration estimates for tasks.
Customize Project views to meet your needs.
Chapter 1
IN THIS CHAPTER
Understanding the elements of a project
Laying out the project manager’s role
Benefitting from Project 2019
Exploring the software interface
Finding help in Project
Welcome to the world of computerized project management with Microsoft Project. If you’ve never used project management software, you’re entering a brave new world.
Everything you used to do with handwritten to-do lists, sticky notes, word processors, and spreadsheets magically comes together in Project. However, this transition doesn’t come in a moment, and you need a basic understanding of what project management software can do to get you up to speed. If you’ve used previous versions of Project, the overview in this chapter can refresh your memory and ease you into a few of the new Project 2019 features.
Even if you’re a seasoned project manager, this chapter provides the foundation for how to work with Project.
You probably handle projects day in and day out. Some are obvious, because your boss named them so that any fool would know that they’re projects: Acme Drilling Project or Network Expansion IT Project, for example. Others are less obvious, such as that presentation you need to put together for your director or that how-to guide on planting a vegetable garden in your backyard.
In this book, a project is defined as a unique venture undertaken to produce distinct deliverables, products, or outcomes. In the context of a project, a deliverable is an individual component or item that meets the requirements of the project, such as a design document or a prototype. Projects have multiple variables; some are straightforward to define, and others aren’t.
Using the information about variables in Table 1-1, you can say that project management is the practice of organizing, managing, and controlling project variables to meet the project outcomes and mission.
TABLE 1-1 Project Variables
Variable |
Description |
Defined |
|
Scope |
The work needed to produce the deliverables, products, or outcomes for the project. |
||
Time |
The duration required to complete the project work. |
||
Cost |
The funds required to complete the project. |
||
Resources |
The people, equipment, material, supplies, and facilities needed to accomplish the project. |
||
Undefined |
|||
Change |
The type, timing, number, and degree of modifications from a project baseline; can affect the project’s scope, time, cost, or resources. |
||
Risk |
Uncertainty (associated with the scope, time, cost, resources, stakeholders, or environment) that can threaten the completion of any aspect of the project. Fortunately, risks can also present opportunities to accelerate the schedule or come in under budget. |
||
Stakeholder |
A person who can affect, or who is affected by, the project, either positively or negatively. |
||
Environment |
The location, culture, or organization in which the project occurs. |
Although understanding the role (let alone the usefulness) of certain managers isn’t always easy, you can easily spot the value of a project manager: This person creates the master plan for a project and ensures that it is implemented successfully. Along the way, the project manager uses technical, business, and leadership skills to manage the completion of tasks and keep the schedule on track.
A project manager isn’t always the highest authority in a project. Often, that role belongs to whoever manages the project manager — including, possibly, members of senior management. Rather, the project manager is the person who ensures that aspects of the project are integrated and assumes hands-on responsibility for successes as well as failures.
The project manager manages these essential pieces of a project:
Creating a logical balance of the defined variables of scope, time, cost, and resources is at the core of a good project manager’s job throughout the life of a project. Managing a project requires overseeing all its variables to ensure that the project goals are accomplished on time, within the limits of the budget, and using the assigned resources while also addressing risks, managing change, and satisfying stakeholders. Sound easy? Maybe not. However, one thing is certain: Having software to help organize and structure the work makes managing the project less daunting. That’s where Project 2019 can help.
Project 2019, which is a scheduling tool, helps you organize, manage, and control defined variables, as identified in the preceding section. Project can also help you manage the undefined variables as well. In this book, I show you how to use Project to organize and manage your work, create realistic schedules, and optimize your use of resources.
Take a moment to look at some of the wonderful ways in which Project can help you organize, manage, and control your project. Now that you have, or your company has, bought Project (and this book) and you’re investing your time to understand how to use it, you can enjoy these benefits:
The file you create in Project is a Project schedule model. It’s a model because it models what you think will happen given what you know at the time. However, for ease of reference, I just refer to it as a schedule. The schedule has a plethora of data about various aspects of your project as well as graphical representations of that information.
When you first open Project 2019, you see several options for starting a new project, as shown in Figure 1-1.
FIGURE 1-1: What you see when you open Project 2019.
You can open a blank project, create a new project from an existing project, or create a new project by importing information from Microsoft Excel or SharePoint. You can also take advantage of premade templates for common project types, such as these examples:
If you don’t see the template you need, you can search for online templates by entering keywords in the search box at the top of the page. For purposes of this discussion, I assume that you’re starting with a new, blank project.
When you open a new project, you see the Quick Access toolbar, a few Ribbon tabs, the Ribbon, the Timeline, a pane with a sheet and a chart, and the status bar, as shown in Figure 1-2.
FIGURE 1-2: A blank project.
In Figure 1-2, you see Gantt Chart view. (I discuss views in Chapter 6.) For now, here’s an overview of the major elements in Project (refer to Figure 1-2):
Each of the Ribbon tabs in Project shows different options on the Ribbon. In this section, I provide an overview of each Ribbon tab and of the Ribbon and the Quick Access toolbar. I elaborate on various functions and commands on the Ribbon in later chapters.
Each Ribbon tab has a different group of controls or functions. You can navigate from one tab to another by clicking on the tab name.
The first tab on the left is the File Ribbon tab. After you click this tab, you see the Navigation plan down the left side, as shown in Figure 1-3.
FIGURE 1-3: The File Ribbon tab menu.
The Ribbon tab puts you into Backstage view, where you find choices for working with files and changing options. For example, you can create a new project, open an existing project, save your current project, or print your current project. From Backstage view, you can also share, export, or close your current project. If you’re feeling adventurous, you can click Options and customize the Ribbon and the Quick Access toolbar.
The Task Ribbon tab is where you spend a lot of your time in Project. As you can see in Figure 1-4, on the far left side of the Task Ribbon tab is the View. The default view is Gantt Chart view. It shows the task information and the chart that displays a bar chart representing the duration of each task.
FIGURE 1-4: The Task Ribbon tab.
In addition to Gantt Chart, you can choose these views:
Calendar |
Network Diagram |
Resource Sheet |
Resource Usage |
Resource Form |
Resource Graph |
Task Usage |
Task Form |
Task Sheet |
Team Planner |
Timeline |
Tracking Gantt |
You may recognize some of the groups of commands on the Task Ribbon tab. For example, the Clipboard and Font groups are standard in many Windows applications. Other groups, such as Schedule and Tasks, are specific to a particular view — in this case, Gantt Chart view. Look for the Gantt Chart Tools above the Format tab when you see the Task Ribbon tab in Gantt Chart view. In other views, you see different tools above the Format tab.
The Resource Ribbon tab, shown in Figure 1-5, helps you organize resources, such as assigning and leveling resources across tasks. In Project, resources include people, equipment, material, locations, and supplies. You can assign costs and calendars to resources. (I talk more about resources in Chapter 7.)
FIGURE 1-5: The Resource Ribbon tab.
The Report Ribbon tab, shown in Figure 1-6, is where you can create reports on resources, costs, or progress, or put them all together in a dashboard report. You can create a report that compares your current status to previous versions of your project. I tell you all about reports, including how to customize and export your reports, in Chapter 18.
FIGURE 1-6: The Report Ribbon tab.
On the Project Ribbon tab, shown in Figure 1-7, you find commands to help you manage your project as a whole, rather than by task or resource. For example, you can enter or change the project start and finish dates and the baseline. If you need to change working time or add a subproject, this is the place to do it.
FIGURE 1-7: The Project Ribbon tab.
The View Ribbon tab, shown in Figure 1-8, lets you see some standard views. Examples are Task views, such as Gantt Chart, and Resource views, such as Resource Usage or Team Planner. You can use the View Ribbon tab to look at information sorted by date or a specific period. This tab also lets you see the entire project, show or hide the Timeline, and set the timescale you see.
FIGURE 1-8: The View Ribbon tab.
The Format Ribbon tab, shown in Figure 1-9, has commands that help you present your schedule, such as text styles, Gantt chart styles, and column settings.
FIGURE 1-9: The Format Ribbon tab.
FIGURE 1-10: Keeping your Ribbon visible.
The Quick Access toolbar, which appears onscreen at all times, initially contains the Save, Undo, and Redo buttons. You can customize the Quick Access toolbar by clicking the down arrow at the right end of the toolbar and clicking the option you want to hide or display.
If you don’t see the option you want, click More Commands near the bottom of the menu to display the Quick Access Toolbar category in the Project Options dialog box. This shows you a full list of commands you can add. Figure 1-11 shows the list of commands you can choose from.
FIGURE 1-11: Customizing the Quick Access toolbar.
The nifty Timeline tool shows the entire scaled time span of the project. To show the Timeline, go to the View Ribbon tab (shown in Figure 1-8), in the Split View group and click the check box that says Timeline. You can add tasks or milestones to the Timeline. You can also copy the Timeline and paste it into reports or other presentations. To hide the Timeline, uncheck the Timeline box. You can also work with the Timeline by right-clicking to insert tasks, copy the Timeline, change the font, or view detailed information. Figure 1-12 shows the Timeline with summary tasks and milestones.
FIGURE 1-12: The Timeline.
The status bar, shown in Figure 1-13, sits at the bottom of the project, to indicate whether your tasks are manually or automatically scheduled. (Read more on this topic in Chapter 2.) The status bar also lets you move quickly to some of the most popular views, such as Gantt, Task Usage, Team Planner, Resource Sheet, and Reports. You can also adjust the time scale from a high-level, time scaled view to a detailed time-scaled view with the View slider, on the far-right end of the status bar. I talk more about views in Chapter 6.
FIGURE 1-13: The Status bar.
In previous versions of Microsoft Office, there was a Help function. That has been replaced by the Tell Me What You Want to Do feature. If you want some coaching on how to do something in Project 2019, just click the light bulb next to the Format tab. Enter a keyword, and you have several options to choose from. I searched on “critical path” and the information in Figure 1-14 came up.
FIGURE 1-14: A search for “critical path.”